Go for it! Longyuan Construction Group Poly Nanjing Lot N0.2022G05 successfully completed the pre-sale node
tenmonthtwenty-onePoly Nanjing, undertaken by Longyuan General Contracting Management CompanyG0fiveprojectfive號樓(lóu)二層疊合板開始吊裝(zhuāng),標誌著(zhe)該project首開樓Building圓滿完成建設單位設定的節(jiē)點目標。
Poly NanjingN0.2022G0five地(dì)塊(kuài)project位於(yú)南京市雨花台區,project總建築(zhù)麵積約nine6fourthirty-two.2five Square meters, mainly including the basement of the first floor (partial second floor) andfourBuildingthirty-twoA high-rise residential building with two storeys.

project開工以來,受天氣、土方外運等多種因素影響,根據建設單位(wèi)製定(dìng)的預售節點目標,首開(kāi)樓Building(five#Building) construction period onlythirty-twoDays.five#The structure of the building is very complex, including two underground floors and several personal mouth guards. In addition to the recent high temperature and rainy weather, the repeated COVID-1nine and the National Day holiday, the task is very arduous.
Longyuan Construction Group has always unswervingly promoted the strategy of key customers and focused on the management of key customers. NanjingG0fiveproject是總承包管理公司(sī)在江蘇(sū)區域承接的第二個保利地產project,集團公司高度關注,要求project部全力(lì)趕工,保質保(bǎo)量完成節點。
在project經理(lǐ)彭福鬆(sōng)的帶(dài)領(lǐng)下,project團隊迅速統一(yī)思想,製定科(kē)學的進度計劃和資源組織計劃,合理(lǐ)穿插,爭取時間。project管理團(tuán)隊鉚足幹勁,攻堅不怕苦,老(lǎo)員工(gōng)充分(fèn)發(fā)揮了經(jīng)驗豐富的作用,成為project團隊運行(háng)的錨錠。年輕員工幹勁(jìn)十足,多次熬更守夜,為搶工期、保質量作出了重要(yào)貢(gòng)獻。總(zǒng)承包管理公司負責人也多次深入(rù)project現場調研督導,解決問題。
With the full efforts of all staff,ninemonththirtyDay,five#The floor concrete pouring is completed;tenmonthelevenDay,完成負二層混凝(níng)土澆築;tenmontheighteenDay,完成負一層混凝土澆築,最終順利完成預售節點,完美履約,贏得了(le)建設單位的高(gāo)度認(rèn)可(kě)和讚譽。

The general contracting management company will continue to strive to improve its own management level, devote itself to creating high-quality projects, establish a good brand image of the company, and contribute to the company's promotion of key customer strategy and further market development. & nbsp;